ImpactFeeAtlasCompare fees
CityUtah CountyVerified Jun 19, 2026

Provo, UT Development Impact Fees (2026)

Normalized development impact fees, water & sewer connection (tap/SDC) fees, and mitigation fees for Provo, Utah — per dwelling unit, by category, with links to every official source.

$17,085
Total per single-family home
impact + connection fees
$5,034
Impact / development fees
roads, parks, schools…
$12,051
Water & sewer connection
tap / capacity / SDC
$6,391
Per multifamily unit
total fees / unit

What a single-family home pays in Provo

$17,085 total per unit across 5 fee categories.

  • Water connection (tap / SDC)$7,600
  • Sewer connection (tap / SDC)$4,450
  • Parks & recreation$3,105
  • Transportation / roads$1,293
  • Public safety$636

Provo’s $17,085 is close to the Utah tracked median of $16,967.

Full fee schedule — single-family

Impact / development fees

Fee (local term)BasisAmountSource · effective
Transportation / roads
Road Impact Fee — One-Family Dwelling — Road impact fee is organized by ITE Land Use; residential is charged per dwelling unit (a flat per-unit dollar amount already derived from ITE trip rates, NOT a per-trip rate the builder computes).
per dwelling unit$1,293Provo City, Utah
Jul 1, 2025High
Parks & recreation
Park Impact Fee — One-Family Dwelling — Park (parks & recreation) impact fee per single-family dwelling.
per dwelling unit$3,105Provo City, Utah
Jul 1, 2025High
Public safety
Public Safety Impact Fee — Single-Family — Provo levies a MERGED Public Safety impact fee — there is NO separate Fire fee and NO separate Police fee. The live Effective July 1, 2025 single-family value is $636.30 (currently in force; the next row, eff. July 1, 2026, = $647.97). The previously-known merged $636.30 happens to match the current live value.
per dwelling unit$636Provo City, Utah
Jul 1, 2025High
Drainage / stormwater
Stormwater Impact Fee (per acre) — Stormwater/drainage impact fee is charged per ACRE of development, not per dwelling unit, so it is not part of the flat per-unit SFD total. FY 2025-2026 row is currently in force (today 2026-06-19); next row FY 2026-2027 = $8,542.64.
alternative · not added to total
per acre$8,263Provo City, Utah
Jul 1, 2025High

Water & sewer connection fees

Fee (local term)BasisAmountSource · effective
Water connection (tap / SDC)
Water Resource Impact Fee (Standard Lot, 0.15–0.3 acres) — Provo charges residential water impact fees per dwelling unit, tiered by lot size, NOT per meter. Standard Lot = 0.15–0.3 acres; this is the representative single-family detached row. Effective July 1, 2025 row is currently in force (through June 30, 2026). Next year (eff. July 1, 2026) = $7,622.10.
per dwelling unit$7,600Provo City, Utah
Jul 1, 2025High
Water connection (tap / SDC)
Water Resource Impact Fee (Small Lot, <0.15 acres) — Small Lot tier (<0.15 acres). Mutually exclusive variant of the lot-tiered single-family water fee. Large Lot (>0.3 acres) has no flat figure — calculated individually per the multifamily methodology — so it is omitted.
alternative · not added to total
per dwelling unit$4,930Provo City, Utah
Jul 1, 2025High
Sewer connection (tap / SDC)
Sewer Impact Fee (per ERU) — A single-family detached residence = 1.00 ERU, so the SFD sewer impact fee is $4,450.26. (Non-standard/commercial sewer is computed per drainage fixture unit.) No year-by-year effective date table shown for sewer.
per dwelling unit$4,450Provo City, Utah
Jul 1, 2025High

Full fee schedule — multifamily

Impact / development fees

Fee (local term)BasisAmountSource · effective
Transportation / roads
Road Impact Fee — Multifamily (3-9 stories) — Mid/high-rise multifamily road fee per dwelling unit. Representative multifamily road row.
per dwelling unit$961Provo City, Utah
Jul 1, 2025High
Parks & recreation
Park Impact Fee — Multifamily Dwelling (per unit) — Park impact fee per multifamily dwelling unit.
per dwelling unit$2,885Provo City, Utah
Jul 1, 2025High
Public safety
Public Safety Impact Fee — Multifamily — Merged Public Safety impact fee for multifamily, per unit. Effective July 1, 2025 row (current).
per dwelling unit$285Provo City, Utah
Jul 1, 2025High

Water & sewer connection fees

Fee (local term)BasisAmountSource · effective
Water connection (tap / SDC)
Water Resource Impact Fee — Multifamily Indoor (Standard Unit) — Multifamily water = indoor (per unit, by unit size) + outdoor (per irrigated acre). Standard Unit is the representative MF indoor row. Small Unit = ≤1 BR, ≤1 BA, ≤1,000 SF.
per dwelling unit$2,261Provo City, Utah
Jul 1, 2025High
Water connection (tap / SDC)
Water Resource Impact Fee — Multifamily Indoor (Small Unit) — MF indoor Small Unit variant (≤1 BR/1 BA/≤1,000 SF). Mutually exclusive with Standard Unit.
alternative · not added to total
per dwelling unit$1,281Provo City, Utah
Jul 1, 2025High
Water connection (tap / SDC)
Water Resource Impact Fee — Multifamily Outdoor (per irrigated acre) — Outdoor water demand component for multifamily, charged per irrigated acre (additive to the per-unit indoor fee, not a per-unit figure).
alternative · not added to total
per acre$29,168Provo City, Utah
Jul 1, 2025High

Coverage & caveats

Complete residential impact-fee set read VERBATIM from the LIVE adopted Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/FS_Impact), accessed via a real browser session that passed the Cloudflare/Turnstile bot check on 2026-06-19. Provo levies the following impact fees: (1) Water Resource Impact Fee — per dwelling unit, TIERED BY LOT SIZE (Small Lot <0.15 ac, Standard Lot 0.15–0.3 ac, Large Lot >0.3 ac calculated individually with no flat figure); NOT meter-based for residential (meter size applies only to nonresidential). The Standard/Small Lot figures ($7,600.34 / $4,930.43) are REAL and CURRENT — a prior pass wrongly flagged them as fabricated; they appear verbatim as the Effective July 1, 2025 row in the live schedule. (2) Sewer Impact Fee — $4,450.26 per ERU (1.00 ERU = SFD). (3) Road Impact Fee — per dwelling unit by ITE land use ($1,293.06 SFD). (4) Park Impact Fee — per dwelling ($3,105.10 SFD). (5) Public Safety Impact Fee — a MERGED Fire+Police fee ($636.30 SFD, eff. 7/1/2025); there is NO separate Fire fee and NO separate Police fee. (6) Stormwater Impact Fee — per ACRE ($8,262.93 FY2025-26), not per unit. (7) Power/Energy Impact Fee — amperage-based electric utility connection charge (not a standard per-dwelling fee, so not modeled as a per-unit residential row). Categories that DO NOT EXIST in Provo: no school impact fee (Utah does not authorize school impact fees), no library impact fee, no separate general-government/municipal impact fee. All figures are the currently-in-force rows (Effective July 1, 2025 / FY 2025-2026) as of today, 2026-06-19; the next-year rows (eff. July 1, 2026) take effect in ~12 days.

Representative single-family detached per-unit total is built from these non-excluded SFD per_dwelling_unit rows: Water Resource (Standard Lot) $7,600.34 + Sewer (per ERU) $4,450.26 + Road (One-Family Dwelling) $1,293.06 + Park (One-Family Dwelling) $3,105.10 + Public Safety (Single-Family) $636.30 = $17,085.06. Excluded from the flat SFD per-unit total: Small Lot water variant, all multifamily rows, the per-acre water outdoor component, and the per-acre stormwater fee (these are either mutually-exclusive variants or area-based, not per-unit). Power/Energy impact fees are amperage-based and not included.

Sources

1 official source · 14 high-confidence figures.

  1. 1Provo City Consolidated Fee Schedule — Impact FeesProvo City, Utah · fee schedule · effective Jul 1, 2025 · retrieved Jun 19, 2026

Provo impact fees — FAQ

How much are development impact fees in Provo, UT for a single-family home?
As of 2026-06-19, total development fees for a single-family detached home in Provo are about $17,085 per unit — roughly $5,034 in impact/development fees plus $12,051 in water/sewer connection fees. Figures are normalized from official sources; verify with the jurisdiction before relying on them.
What are the impact fees per multifamily unit in Provo, UT?
Total development fees for a multifamily unit in Provo are about $6,391 per unit as of 2026-06-19.
Are impact fees in Provo the same as building permit fees?
No. Impact fees (and water/sewer connection fees) fund off-site capital — roads, parks, schools, utilities — and are charged per new dwelling unit. Building permit and plan-review fees are separate and are not included here.
How often do Provo's impact fees change?
Most jurisdictions adopt fees by ordinance and escalate them annually (often by a construction cost index), with occasional mid-year updates. Always confirm the current adopted schedule with the jurisdiction. ImpactFeeAtlas last verified Provo on 2026-06-19.

More Utah jurisdictions